Binding ConstraintPilgrim-West Bus 138kV PAR
ASDU Total Cost$520.6M
CY23 Queue Depth2,477 MW
Storage ICAP0 MW delivered
LIPA Import Limit1,621 MW (ATBA normal)
LI Byway SDUPAR $295M + 5 supporting upgrades
All 10 CY23 ASDU projects here — 825, 957, 971, 1012, 1117, 1123, 1254, 1255, 1256, 1257. Q680 Juno Power Express (1,200 MW) fully deliverable — separate POI. DEC Peaker Rule: Shoreham 67MW + Glenwood 55MW + Northport 14MW deactivated (LIPA reliability waiver expired May 2025). Nassau Energy 52MW retired. 5 of 10 ASDU projects completed. 0 MW battery storage currently delivering ICAP in Zone K.
0 MW battery ICAP in market — 2,477 MW queued. The entire Zone K storage buildout is still in the pipeline.